New Welcome Center Updates

January 21, 2010

Although it has been a while since we posted photos of the Welcome Center progress a lot has been happening. Work continues on installing the utilities for the building (part of the building has been sealed off so that work can be done in the cold). Concrete is being poured on the first floor and work on the exterior skin of the elevator shaft continues.  In addition to work on the building, construction of the retaining wall for the bridge that will go over the bioswale has also started.  Continue to check in on our progress here or in person - the gardens are spectacular in the snow!


The first floor of the building, looking West.


The elevator shaft, looking South.


The foundation for the bioswale bridge, looking South.


The bioswale bridge, looking East.

December 16, 2009

There has been a lot of exciting construction going on over the last week - the elevator shaft concrete mold was completed, electrical lines were put in, the steel arrived and the frame started going up.  As you can see from the pictures below - the building is really shaping up!

December 4, 2009

We're moving right along... over the last two weeks work was completed on a second story wall (the tall concrete structure on the left in the picture below) along with installation of waterproofing and insulation materials and sanitary lines.
A view from atop the Knoll looking down on the building (the tall structure in the left-hand background is the elevator):

A view from the temporary parking area:

Our weekly overview of the site:

November 20, 2009

The Nevin Welcome Center is really starting to take shape, here you can see its development from Judd Falls Road, looking west beyond the Lewis Building.

This week soil was brought in to start backfilling around the building now that the foundation is set.
 
Here's another overview image:

This week we also saw the start of the new driveway:

November 13, 2009

This week the building continued to take shape with the molds for the elevator and interior second story walls being constructed.  Work also started on the irrigation lines, data and voice lines.  Additionally LEED dumpsters were delivered and placed on site. These dumpsters are for separating and recycling of used construction material.

November 6, 2009

Here's an overview of the site, you can really start to make out the building in the background:

Here you can see the outline of the building's foundation:

Work will begin on the elevator shaft next week:

The new walkway/service driveway from the parking area to the building was started this week:

October 30, 2009

More foundation work this week.

Along with some work on the bioswale:

October 23, 2009

A view of the site from Comstock Knoll:

Reinforcing rods and footers are going in:

October 16, 2009

The building's foundation continues to take shape.


The new driveway/walkway is being formed.

October 9, 2009

Another week of exciting developments on the construction site - it's amazing how quickly the building is starting to take shape.  This week work on the building's foundation continued and the first recognizable element of the building - the elevator shaft was started (pictured below - it's the black and red box in the foreground).


Some overview shots of the site from Conifer slope: