Top Navigation

Update: Cascadilla Gorge Trail repair

Published: 
2 years 50 weeks ago

Cascadilla Gorge is scheduled to open next June. Here is what is happening now to keep that date on track:

New gate at the “lower” gorge entrance: A custom-made iron gate was installed at the gorge entrance at the Treman Triangle off of Linn Street. It will allow us to close the trail each winter when trail conditions are unsafe.  Designed by local artisan Durand VanDoren, the 1200 pound gate was inspired by the gorge’s cascading falls, and oak leaves and acorns found on an historic Cascadilla Glen Trail plaque.

New staircase under the Stewart Avenue bridge: The staircase leading to the iconic stone bridge that crosses the creek will soon follow a new, safer path. The staircase was designed to fit into the gorge landscape, provide a more direct view of the adjacent waterfall, and move visitors farther from an overhanging, unsafe gorge wall. A dam (shown above) was built with sandbags and concrete blocks and a water pump was used to keep the water level low to build the new stairs.

Stabilizing the 150-year-old retaining wall near historic Eddy Gate: This 60 foot tall structure was constructed to stabilize and retain the gorge wall after stone was quarried from the gorge to construct Cascadilla Hall.

 

Completing this gorge restoration project is one part of several recommendations to increase gorge safety approved by Cornell President David Skorton. Read about the additional recommendations in the December 4th Ithaca Journal article, "Cornell committee proposes safety steps for gorge."